Rasberry Field Update

This week we are replacing the pumping unit on #1403 well that was damaged and has not been pumping for while now. A previous attempt to repair the old unit proved unsuccessful, so we are switching it out with another one in the field that was idle. This well is completed in the Strawn formation so we are anxious to get it back on line and producing. The well was last making about 7-10 bopd before it went down.

We are waiting on delivery of the new injection pumps and hope to get them installed in the next two weeks, this will help to give us more capacity to move more fluids in the field for the current and future planned wells. Cheers!



Recent Posts

See All

Rasberry Field Update

With the 1302-H well on line and the other wells in the field we are making a substantial amount of saltwater that is re-injected into...